It is true
that all journeys begin with a single step and in the case of a
telecommunications infrastructure and/or hardware project that first step is
the creation of the Request for Proposal (RFP).
The
RFP is a document that sets the tone for the entire project. A well thought out
and well-written RFP goes a very long way to insure the success of the project.
On the other hand a poorly thought out and badly written RFP will most
certainly gaurantee that the project becomes a nightmare.
The
best way to think of an RFP is as a combination of a guide book, a map and a
rule book. It is a document that defines the goals, defines the project and
defines the terms of engagement between the parties. As such it should be a
document that clearly articulates all of the above. It should also be a
document that is designed to be fair to all parties involved in the project.
Having
been on both sides of the fence on this issue I have seen the affect that the
RFP has on both parties and upon the overall success of the effort. One of the
mistakes that I have seen made is that often times the “buyer” and
the “vendor” see the RFP as a tool to take advantage of the other
party.
This
is most unfortunate because it sets the stage for an adversarial relationship
right from the beginning.
The
best way to avoid such a scenario from occurring is by making sure that the RFP
is used as a tool to clearly describe the scope of the project; the
buyer’s requirements and expectations of the vendor; the responsibilities
of all parties involved. Since it is to be used a “rule book” it
must be designed to promote fairness, thereby establishing the tone of the
“spirit” of the upcoming working relationship.
In
order to create such a document there is a lot of preplanning that must take
place on many levels often times involving many people in order to insure that
as many of the issues associated with the effort are identified, defined,
addressed and properly articulated in the document.
It
is important to remember that although the project involves the installation of
technology the actual act of conducting that business involves many departments
of the organization outside of the technology group. This could include
finance, facilities and legal departments as well as the departments that are
getting the new network.
And
perhaps the
The
following is a list of guidelines to follow when writing an RFP and some
implementation suggestions. By following these steps you will be able to avoid
many mistakes that could become very costly throughout the duration of the
project and/or the relationship.
Afterall,
regardless of how much ink is used to contractually try to tie someone up, it
is the “spirit” of the agreement under which everyone operates that
really works to make a project successful.
What Makes a
good Bid Specification?
·
Is
it Fair?
·
Does
it Work to Insure Only Competent Bidders Will Meet the Contractor
Qualifications?
·
Is
it Non-Discriminatory?
·
Does
It Communicate the Objectives and the Wishes of the Client Clearly and
Accurately?
·
Does
it Provide for Protection of Both the Client and the Service Provider?
·
Does
it Provide for Opportunities for Dialog Between the Parties? i.e. Mandatory
Site Walkthroughs, Regular Progress Meetings?
·
Does
it Define Payment Terms?
·
Does
it Define the Relationship of the Parties?
·
Does
it Address Change Order Procedures?
Key Components of an Effective Bid Specification and/or Request for Proposal (RFP)--Summary
·
Preplanning:
Internal Analysis
·
Initial
Concepts: Internal (No Vendors)
·
Vendor
Selection: Contract Negotiations
·
Project
Administration
·
Cutover
Implementation of the Specification--Detail
Preplanning:
Internal Analysis
·
Educate
yourself as to the components of the system to be specified and some of the
options available to you.
·
Evaluate
specific desired features and functionality of the proposed system, required
peripherals, interfaces and expectations for life cycle and warranty period.
·
Solicit
departmental/organizational input for desired features requirements, financial
considerations.
·
Determine
most cost efficient solution for one year, three year and, perhaps, five year
projections.
·
Evaluate
unique applications/transmission requirements, departmental or operational
requirements/restraints, wireless, voice messaging, fiber, etc.
·
Other
site specific concerns.
Initial
Concepts: Internal (No Vendor Invovlvement)
·
Analyze
perceived vs. actual needs/requirements of features and functionality, future
applications, system upgradeability, etc.
·
Discuss
language that is geared towards defining contractor qualifications. Strongly
consider requirements that call for vendors to be certified by the
infrastructure component manufacturer whose products they are proposing to
install. The same holds true for hardware bids. It is important that any vendor
selling hardware be an authorized reseller a hardware component manufacturer.
Call for proof demonstrating each certification as part of the initial bid
submittal.
·
Prepare
draft outline of selected requirements and acceptable timelines. (Subject to
minor changes by mutual agreement)
·
Prepare
a detailed RFP, including scope of work; testing acceptance; proposed payment
schedules; liquidated damages; restoration; licensing; permits; fees; milestone
dates (to include, bid conference dates; walk through dates; date to submit bid
clarification questions; bid due date) etc.
·
Call
for all pricing to be in an itemized format, listing components to be
installed, quantities to be installed, unit and extended price.
·
Request
that costs to add or delete circuits-on a per circuit basis-be included in the
response to the RFP.
·
Include
detail language addressing the “Intent” of the bid. Such language
should articulate that the intent is to have a system installed that contains
all of the components necessary to create a fully functional system. Language
should be included calling for the contractors to address any omissions in the
bid that would prohibit the system from being fully functional at time of
contract completion.
·
Insure
that you allow for adequate time for detailed site survey/estimating.
·
Upon
receipt of bids narrow field to three finalists.
·
Correlate
information and prioritize or rank three remaining bids on cost vs.
performance.
·
Schedule
meetings and/or additional surveys for best-and-final bids from remaining
vendors.
Vendor
Selection: Contract Negotiations
·
Select
vendor based upon criteria that includes, but is not limited to: balance
between cost/performance, engineering design and innovative solutions, proven
expertise in projects of similar scope, size and complexity and quality
craftsmanship/conformance with all appropriate codes, ordinances, articles and
regulations.
·
Insist
on detailed warranty of system life cycle. Consider ability to perform and any
other requirements deemed necessary to execute the intent of contract.
·
Present
a detailed description of work to be performed, payment agreements, and
compliance with items contained in the RFP. Include in contract.
·
Identify
key project personnel, from both sides of the agreement and the staff
associated with accountability/responsibility for making decisions.
Project
Administration
·
Schedule
regular progress meetings. Progress reports should be submitted and compared to
milestones. Accountability to be assigned with scheduled follow-up and
scheduled resolution dates.
·
Contractor
supervision to perform 100% quality inspections of work performed and maintain
records to be submitted at progress meetings.
·
Contractor
should maintain and provide As-Built documentation. The documentation may
include: outlet locations, circuit numbers, telecommunication closet locations,
trunk and distribution routing.
Cutover:
·
Cutover
preparation should begin 5 to 15 days prior to scheduled date, unless otherwise
mutually agreed upon.
·
Cutover
personnel and backups should be designated and scheduled well in advance.
·
Cutover
personnel should have access to all records, diagrams, drawings or other
documentation prepared during the course of the project.
·
Acceptance
should begin at the completion of the cutover and could continue for a period
of 5 to 10 working days prior to signing. Warranty should begin immediately
upon signing of acceptance.
·
Acceptance
criteria should include 100% of all circuits installed. All circuits should
pass specified performance tests, and be duly documented and recorded in the
project history file and cable management systems.
By
following these guidelines, or at least the ones that apply to your particular
situation, you can greatly reduce the chances of any aspect of your project
from spiraling out of control.